Choose production system settings

Find out how component recalculation, production hours and production days affect your assemblies.

Written by Heather Worthington

These system settings control how Unleashed calculates and schedules your assemblies. A setting applies to transactions from the time you turn it on, and open transactions that already exist don't update.


Open the system settings

You can find all system settings in the Settings tab of the Company page.

  1. From the main menu, click Settings, then click Company.

  2. Click the Settings tab.

  3. Turn on or set the options you need.

  4. Click Save.


Recalculate Component quantities

This setting controls what happens to component quantities when you change the assembled quantity:

  • Turned on: Unleashed asks whether to update the components proportionally, based on the Bill of Materials (BOM).

  • Turned off: Unleashed recalculates all component quantities automatically.

This setting can be enabled or disabled at any time.


Production Hours Per Day

Production Hours Per Day sets how many hours of production you run each day, from 1 to 24. The default is 8 hours. Unleashed uses it to calculate assembly start dates from your Assemble By deadlines.

📌Note: Unleashed uses this value on all BOMs, unless a BOM has its own number of production hours per day.


Production Work Days

Production Work Days sets which days production runs, so your assembly scheduling is accurate. The default is Monday to Friday.

📌Note: Unleashed uses these days on all BOMs, unless a BOM has its own production days.